Creston School Board decides AEA site for bus garage

Text Size: AaAaAaAaAa
This photo shows the damage at the former bus garage at Creston High School after an EF2 tornado swept through the northern part of Creston April 14, 2012.

At a special Creston School Board meeting Monday, the board voted to place the bus garage at the AEA site west of Creston High School.

Roy Stroud, Creston School District business manager, discussed with the board members, interim Superintendent Chuck Scott and Gary Briley, maintenance director of Creston School District, the basic design of the bus garage. Board Member Galen Zumbach was not present. The placement was passed with a 3-1 vote, with Ron Dunphy voting no.

"First of all, I don't think we have a clue what it's going to take to prepare that site," said Dunphy. "And if we put the bus barn there it's not just about preparing 300 feet of depth to place that building, we're talking about extending access to it clear over to our propery ... I don't know that it works with the AEA, but my thought is no, don't use it."

The former AEA site is located at1405 S. Lincoln St. The bus garage would consist of a steel building with 14 stalls, three service bays and a wash bay. Every two buses get one 24-feet-tall double door, and the floor will be gravel. The building will also contain offices, a break room and storage.

"Actually I think our intent was to even have 50 feet available for a bus, which gave you space on each end, knowing that the small vehicles, none of them could be longer than about 18 feet, so we gave 25 feet for them," said Stroud.

The building is sized so the entire bus fleet and small vehicle fleet would be able to fit inside the cold-storage unit.

"I know a lot of districts don't have their buses under storage and this is going to be an experience this winter, I think ... But you know, you get a freezing rain or something, how many hours are going to be spent trying to warm a bus up, and fuel costs, trying to scrape windows? If we don't get the windows scraped good enough and we have an accident? ..." said Briley

The plan for the garage is to use the existing concrete at the AEA site so it will eventually break up and can be replaced when it is the main project to discuss. The dirt work would include leveling and structural fill to be put in. Dirt work is expected to cost more than $60,000, additional utilities is expected to cost more than $70,000, so the total amount will be closer to $150,00 or more.

Previous Page|1||

Comments


Reader Poll

Which upcoming Creston event are you most looking forward to?

Relay for Life
Party in McKinley Park
Elm's Club Bike Night
Creston Fourth of July celebration
Other (Place your answer on the CNA Facebook page)

Top Ads